Update 11 May (by phone)

Mill Lane, Manor Rd, Kettle Close - road closures between 18 May and 6 Jun (not the whole time everywhere though).

Penthorne Close - closure 17 Jun - 8 Jul.

Residents access will be maintained, but controlled.

There is nothing scheduled for Church Lane, Cold Higham.

xxx xxx xxx

Update 1 Apr 20

During these unprecedented times, I wanted to write to you about the work being undertaken in your community to provide residents and businesses with full fibre broadband from Gigaclear.

Gigaclear provides essential internet access services to communities across rural Britain. The Governments 'Key Worker' policy includes utilities and those in the telecoms sector in addition to NHS and emergency services front line staff – amongst others.

Our operation is building and operating a full fibre broadband network to rural areas in England. Never has connectivity been so important within the communities we have built to. Following guidance to take additional precautions and physical distancing, Gigaclear employees and contractors are continuing work in communities where it is safe to do so.

Our customers rely upon our infrastructure and service to keep them connected so that they can work effectively from home, access key public services and continue to educate their children during school closures.

Site teams have been instructed to observe physical distancing guidelines where practical (as advised by the Department for Digital, Culture, Media and Sport) but may need to carry out certain activities and operations where this may not always be possible in order to continue to provide this vital service without disruption.

We will adhere to government advice by continuing our work to provide connected communities. We are also working to help raise awareness about how important our work is – especially now and will be writing to all residents in communities where we are actively building. Please see attached a copy of the letter we will be sending for your reference.

As I write to you, our intention is to carry on with our activities maintaining, building and installing new customers on our network, however, as you will appreciate the situation and guidance changes and we will follow Government advice. More information can be found on our website here: www.gigaclear.com/news/coronavirus

You may also be interested to see the Department for Digital, Culture, Media and Sport press release which was issued on Monday on Government agreed measures with telecoms companies to support communities during this pandemic: www.gov.uk/government/news/government-agrees-measures-with-telecoms-companies-to-support-vulnerable-consumers-through-covid-19

If residents would like to get in touch with us, please ask them to contact our dedicated Network Build Care team on the details below:

Email: networkbuildcare@gigaclear.com

Phone: 01865 591137

If you have any questions or if there is anything I can help with, please let me know.

Kind regards

Louise

Louise Appleton | Community Engagement Manager (Central/North Central)

M: 07790 821873 W: www.gigaclear.com

XXX

Update 13 Mar 20

Gigaclear Operations

Gigaclear Operations to start laying the broadband cable locally will begin shortly. All of the areas mentioned below will have traffic management in place which may cause some minor delays:

From 17th March – 17th April on Butchers Lane.

From 17th March to 30th March on Banbury Lane, Cold Higham

From 24th March to 6th April on Banbury Lane, Fosters Booth.

These are the current plans but could be subject to change.

xxx

Update 2 Mar 20

Ultrafast Broadband is coming to the Parish

As part of the Superfast Northamptonshire initiative to improve rural connectivity, Gigaclear, in partnership with Northamptonshire County Council, will be bringing ultrafast full fibre broadband to Pattishall, Fosters Booth, Grimscote and Cold Higham.

Ultrafast speeds of up to 900Mbs will be available later this year to all households and businesses included in the build programme.

Every home due to receive a connection will be notified in advance of the work commencing to lay the fibre cables to points of termination (connection points) that will be positioned at the boundary of each property on public land. Once this is installed and live, if you then want to take advantage of ultrafast broadband, you will have a choice of internet service providers, including Gigaclear, who can provide the service into your property.

The work is due to start in the next few weeks with the initial phase commencing on Butchers Lane w/c 16th March 2020. This will mean some disruption in the local area while the contractors lay the cables. This will include traffic management at the A5/Butchers Lane junction at times, and digging across driveways.

The fibre cables must be buried in the ground and any public areas impacted by the installation will be fully reinstated in line with statutory regulations and in partnership with the local highways authority.

It is anticipated that the installation will take around 4 - 5 months depending on weather conditions and other utility work taking place in the area.

The Gigaclear team are committed to keeping us fully informed, so expect more information through the post soon. If you have any specific questions about the work Gigaclear will be doing, please send them to networkbuildcare@gigaclear.com or call 01865 591137. For updates, please register your interest on their website gigaclear.com.