Gigaclear Activity

At the minute everything is closed up in Grimscote, it took our contractors a little longer then expected to complete all the works in village, but we are hoping to be back in Grimscote within the next 2-3weeks depending on road space notices being granted with NCC next week.This will include penthrorne close and the rest of mill lane.Church lane has been progressing really well, and all the residents have been very accommodating given the tight space, so I thank them for making it easier for us, we are hoping to be finished here end of next week.Thank you.Kind Regards

Matt HallGigaclear - Project Delivery Lead